How much Concrete do you need?

You can call one of our plants or use the equations below.

Remember to convert all your measurements to feet.
Convert inches to feet: inches / 12. Example 6" / 12 = 0.5'

Slab or Wall Pour:

(Length x Width x Depth) / 27 = cubic yards
Example (top): (20' x 10' x 0.5') / 27 = 3.7 cubic yards

For holes or round piers:

(Radius x Radius) then multiply by 3.14
Then multiply by Height (Depth)
then divide by 27 for cubic yards.
Example ((1.25 x 1.25) x 3.14) x 4 / 27 = 0.73 cubic yards